Board Issues a Reporting Requirement to DOE for a Report and Briefing within 90 Days Detailing Corrective Actions to Bring Savannah River's Procedures into Compliance with the Requirements of Part 830

Document

Key Information

Date
Friday, July 16, 2010
Sender
Dr.Peter S. Winokur
Chairman
Defense Nuclear Facilities Safety Board
Recipient
Thomas P. D'Agostino
Administrator, NNSA