Board Issues a Reporting Requirement for a Report within 60 Days on the Completion of Risk Prioritization Activity with Facility Modifications Should the UPF Milestones be Delayed

From

Dr. A. J. Eggenberger

Chairman
Defense Nuclear Facilities Safety Board
625 Indiana Ave., NW
Washington, DC 20004

To

The Honorable Linton Brooks

Administrator, NNSA
Department of Energy
1000 Independence Ave., SW
Washington, DC 20585

This Letter Pertains To:

Defense Nuclear FacilityY-12 National Security Complex / Oak Ridge National Laboratory