Recommendation 2009-2 Open

Los Alamos National Laboratory Plutonium Facility Seismic Safety

Calendar Information

Monday, October 26th, 2009Date Recommendation Delivered to DOE
Friday, November 6th, 2009Date Recommendation Printed in Federal Register
Monday, December 7th, 2009Due Date for Public Comment on Recommendation
Monday, December 21st, 2009Due Date for DOE Response
Tuesday, February 2nd, 2010Date DOE Response Received
Monday, March 1st, 2010Date DOE Response Printed in Federal Register
Wednesday, March 31st, 2010Due Date for Public Comment on DOE Response
Wednesday, July 14th, 2010Due Date for DOE Implementation Plan
Tuesday, July 13th, 2010Date DOE Implementation Plan Received
Friday, December 17th, 2010Date of DOE Implementation Plan Approval