10/27/1998 |
John T. Conway |
Bill Richardson |
Board Letter Congratulating the DOE on Its Completion of the Dismantlement of W-69 Warheads (Recommendation 98-2) |
PDF |
|
11/20/1998 |
Bill Richardson |
John T. Conway |
DOE Accepts Board Recommendation 98-2 |
PDF |
|
1/15/1999 |
John T. Conway |
Victor H. Reis |
Readiness Review Programs at Pantex Plant |
PDF |
|
3/10/1999 |
Bill Richardson |
John T. Conway |
DOE Requests a 45 Day Extension to Transmit the Recommendaiton 98-2 implementation Plan |
PDF |
|
4/22/1999 |
Bill Richardson |
John T. Conway |
DOE Implementation Plan for Board Recommendation 98-2 |
PDF |
|
5/11/1999 |
Gene lves |
John T. Conway |
DOE Commitment 5.1.4 for the 98-2 Implementation Plan |
PDF |
|
5/18/1999 |
John T. Conway |
Victor H. Reis |
Verification of Process Readiness at Pantex |
PDF |
|
6/3/1999 |
R. E. Glass |
John T. Conway |
DOE Commitments for the 98-2 Implementation Plan and Proposal for Closure of Commitments |
PDF |
|
6/3/1999 |
R. E. Glass |
John T. Conway |
DOE Commitment 5.6.3 for the 98-2 Implementation Plan |
PDF |
|
6/16/1999 |
John T. Conway |
Bill Richardson |
Board Accepts the DOE 98-2 Implementation Plan |
PDF |
|
6/28/1999 |
R. E. Glass |
John T. Conway |
DOE Development & Production Manual Chapter for the 98-2 Implementation Plan |
PDF |
|
6/30/1999 |
R. E. Glass |
John T. Conway |
DOE Albuquerque Operations Office Deliverables for the 98-2 Implementation Plan |
PDF |
|
7/30/1999 |
John T. Conway |
Victor H. Reis |
Review of Status of W62 Disassembly and Inspection Program, Pantex Plant |
PDF |
|
8/6/1999 |
R. E. Glass |
John T. Conway |
DOE Additional Information on Issue Project Plans and BIO Improvement Initiative per the 98-2 Implementation Plan |
PDF |
|
8/23/1999 |
David E. Beck |
John T. Conway |
DOE Decision Report Required in Deliverable 5.5.1(c) for the 98-2 Implementation Plan |
PDF |
|
9/7/1999 |
R. E. Glass |
John T. Conway |
DOE Details on Deliverables for the 98-2 Implementation Plan Due in the Month of August |
PDF |
|
9/10/1999 |
R. E. Glass |
John T. Conway |
DOE Commitment 5.6.1, Pantex Plant ISMSV Phase I Review Plan for the 98-2 Implementation Plan |
PDF |
|
9/21/1999 |
John T. Conway |
Brigadier General Thomas F. Gioconda |
Lightning Protection for Nuclear Explosive Operations at Pantex |
PDF |
|
10/5/1999 |
R. E. Glass |
John T. Conway |
DOE Providing Detail on the Deliverables Due within the Month of September, Recommendation 98-2 |
PDF |
|
10/15/1999 |
John T. Conway |
David E. Beck |
Board Acknowledging Receipt of Deliverable 5.5.1(c) for Recommendation 98-2 |
PDF |
|
11/4/1999 |
R. E. Glass |
John T. Conway |
DOE Deliverables Due for the Month of October for Recommendation 98-2 |
PDF |
|
11/22/1999 |
John T. Conway |
Brigadier General Thomas F. Gioconda |
Board's Increasing Concern Regarding Two Problems that Threaten the Schedule for Stockpile Stewardship that Affects Operations at Pantex and Y-12, Oak Ridge |
PDF |
|
12/1/1999 |
John T. Conway |
Brigadier General Thomas F. Gioconda |
Review of Status of W62 Disassembly and Inspection Program, Pantex Plant |
PDF |
|
12/1/1999 |
John T. Conway |
Brigadier General Thomas F. Gioconda |
Review of Transportation Basis for Interim Operations Module at the Pantex Plant |
PDF |
|
12/6/1999 |
David E. Beck |
John T. Conway |
DOE Orders 452.1B and 452.2B, the Nuclear Explosive Safety Study Group Implementation Guidance and a Letter Requesting Assistance in Recruiting a Senior Panel to Enhance the Quality of Nuclear Explosive Operation Review Process |
PDF |
|
12/10/1999 |
David E. Beck |
John T. Conway |
DOE Revised DOE-STD-3015-97, Nuclear Explosive Safety Study Process, in Completion of Sub-Recommendation 5 of Recommendation 98-2, DOE Proposes Closure of this Sub-Recomendation |
PDF |
|
2/7/2000 |
R. E. Glass |
John T. Conway |
DOE Details on the Deliverables for Implementation Plan 98-2 Due During the Months of December and January |
PDF |
|
3/16/2000 |
Theodore A. Wyka |
John T. Conway |
DOE Response to the Board's Letter Dated February 16, 2000, Requesting Additional Information or Clarification on Presentations and Material Submitted at the Board's Public Meeting |
PDF |
|
4/25/2000 |
Brigadier General Thomas F. Gioconda, USAF |
John T. Conway |
DOE Response to Board Letter Dated December 6, 1999, on Tech 24, Safe Handling of Insensitive High Explosive Weapon Subassemblies at the Pantex Plant |
PDF |
|
4/28/2000 |
R. E. Glass |
John T. Conway |
DOE Update on Deliverables for Implementation Plan 98-2 |
PDF |
|
5/23/2000 |
John T. Conway |
Brigadier General Thomas F. Gioconda |
Review of Tooling, Design, Manufacturing, and Procurement Program, Pantex Plant |
PDF |
|
5/23/2000 |
John T. Conway |
Brigadier General Thomas F. Gioconda |
Analysis of Hazards and Derivation of Controls for Disassembly and Inspection of W76 and W88 |
PDF |
|
7/3/2000 |
Brigadier General Thomas F. Gioconda, USAF |
John T. Conway |
DOE Response to Board Letter Dated March 29, 2000, on Fire Protection Program at the Pantex Plant |
PDF |
|
7/21/2000 |
R. E. Glass |
John T. Conway |
Department Quarterly Report for Implementation Plan 98-2 |
PDF |
|
8/28/2000 |
David E. Beck |
John T. Conway |
DOE Revised Program Directives Governing the Composition and Functioning of the Nuclear Explosive Safety Study Group in Compliance to Commitment 5.4.2(c) of the 98-2 Implementation Plan |
PDF |
|
8/31/2000 |
R. E. Glass |
John T. Conway |
DOE FY 2001 Authorization Basis Upgrade Program Plan to Complete Commitment 4.1.1 of Recommendation 98-2 and Proposal to Close Commitment |
PDF |
|
9/5/2000 |
Theodore A. Wyka |
John T. Conway |
DOE Additional Information or Clarification Requested by the Board on Integrated Safety Management |
PDF |
|
9/25/2000 |
Bill Richardson |
John T. Conway |
DOE Revision 1 to Implementation Plan 98-2, Safety Management at the Pantex Plant |
PDF |
|
10/23/2000 |
John T. Conway |
Bill Richardson |
Board Requests that DOE Provide Documentation and a Briefing on Work Authorization Directives for the Pantex Plant Contractor to Determine Acceptability of Revised Implementation Plan |
PDF |
|
10/31/2000 |
R. E. Glass |
John T. Conway |
DOE Information on Five Deliverables Due October 2000 Relative to Implementation Plan 98-2 |
PDF |
|
11/30/2000 |
R. E. Glass |
John T. Conway |
DOE Information on Three Deliverables Due November 2000 Relative to Implementation Plan 98-2 |
PDF |
|
12/21/2000 |
R. E. Glass |
John T. Conway |
DOE Proposes Closure of Commitment 4.3.8 in Implementation Plan 98-2 |
PDF |
|
1/31/2001 |
R. E. Glass |
John T. Conway |
DOE Provides Information on Outstanding Commitments due Relative to Implementation Plan 98-2, Revision 1 |
PDF |
|
2/22/2001 |
David E. Beck |
John T. Conway |
DOE Informs the Board of the DOE 452 Orders to be Published in May 2001 Relative to Implementation Plan 98-2 |
PDF |
|
2/28/2001 |
R. E. Glass |
John T. Conway |
DOE Provides Information on Outstanding Commitments due January and February 2001 and Proposing Closure of Completed Commitments Relative to Implementation Plan 98-2 |
PDF |
|
3/5/2001 |
John T. Conway |
General John A. Gordon |
NNSA's Enhanced Transportation Cart Plan Does Not Meet the Intent of the Board's Recommendation 98-2; Board Urges DOE to Revise the Plan |
PDF |
|
3/11/2001 |
Brigadier General Thomas F. Gioconda |
John T. Conway |
DOE Response to Board Letter Dated February 27, 2001 on the Implementation of Seamless Safety for the 21st Century (SS-21) for the W76 and W88 Nuclear Explosive Operations at the Pantex Plant |
PDF |
|
3/30/2001 |
David E. Beck |
John T. Conway |
DOE Provides Information on Commitments Due and Outstanding in Relation to Implementation Plan 98-2 and Proposing Closure of Commitments Indicated as Complete |
PDF |
|
4/20/2001 |
Brigadier General Thomas F. Gioconda |
John T. Conway |
DOE Response to Board Letter Dated March 5, 2001 Regarding Concerns on Enhanced Transportation Cart (ETC) Relative to Recommendation 98-2 |
PDF |
|
6/29/2001 |
R. E. Glass |
John T. Conway |
DOE Implementation Plan for Improved Technical Safety Requirement Controls for Fire Protection at the Pantex Plant as Closure of Commitment 4.3.1 |
PDF |
|
12/7/2001 |
W. John Arthur, III |
John T. Conway |
DOE Letter Enclosing Two Deliverables for Implementation Plan 98-2, Revision 1 |
PDF |
|
3/11/2002 |
W. John Arthur, III |
John T. Conway |
DOE Quarterly Report for Implementation Plan 98-2, Revision 1, for the Period Ending December 31, 2002 |
PDF |
|
4/30/2002 |
David E. Beck |
John T. Conway |
DOE Quarterly Report for Recommendation 98-2 for the Period January 1, 2001, through March 31, 2001 |
PDF |
|
7/31/2002 |
David E. Beck |
John T. Conway |
DOE Quarterly Report for Implementation Plan 98-2, Safety Management at the Pantex Plant |
PDF |
|
9/23/2002 |
John T. Conway |
Linton Brooks |
Fire Protection at the Pantex Plant |
PDF |
|
10/23/2002 |
David E. Beck |
John T. Conway |
DOE Third Quarterly Report on the 98-2 Implementation Plan, Safety Management at the Pantex Plant |
PDF |
|
10/28/2002 |
Spencer Abraham |
John T. Conway |
DOE Implementation Plan for Recommendation 1998-2 |
PDF |
|
10/28/2002 |
Spencer Abraham |
John T. Conway |
DOE Changes to the 98-2 Implementation Plan, Safety Management at the Pantex Plant |
PDF |
|
11/15/2002 |
John T. Conway |
Everet H. Beckner |
Board Regarding the Need to Restart Disassembly and Inspection Operations for the W84 Program |
PDF |
|
12/19/2002 |
John T. Conway |
Spencer Abraham |
Board Accepts DOE's Implementation Plan for Recommendation 98-2 |
PDF |
|
1/29/2003 |
David E. Beck |
John T. Conway |
DOE 4th Quarterly Report on the 98-2 Implementation Plan for Fiscal Year 2002 |
PDF |
|
3/18/2003 |
John T. Conway |
Linton Brooks |
Implementation of Fire Protection Controls at the Pantex Plant |
PDF |
|
7/9/2003 |
John T. Conway |
Spencer Abraham |
Board Issues a Reporting Requirement for Briefing by DOE on the Recovery Schedule for Accelerated implementation of SS-21 Tooling for W88 Bay Operations |
PDF |
|
7/30/2003 |
David E. Beck |
John T. Conway |
Quarterly Report for the Period of April 1 to June 30, 2003 for Implementation Plan 98-2 |
PDF |
|
9/30/2003 |
David E. Beck |
John T. Conway |
DOE Provides Status of Commitment 4.4.7 in Implementation Plan 98-2 |
PDF |
|
9/30/2003 |
David E. Beck |
John T. Conway |
DOE Reports Closure of Commitment 4.3.3 in Implementation Plan 98-2 |
PDF |
|
10/31/2003 |
David E. Beck |
John T. Conway |
Quarterly Report for Implementation Plan 98-2 |
PDF |
|
12/22/2003 |
David Beck |
John T. Conway |
DOE Reports Completion of Commitment 4.4.4 in Implementation Plan 98-2 |
PDF |
|
2/3/2004 |
David E. Beck |
John T. Conway |
DOE Quarterly Report for Implementation Plan 98-2, Safety Management at the Pantex Plant, for the Period October 1 - December 31, 2003 |
PDF |
|
4/28/2004 |
David E. Beck |
John T. Conway |
DOE Quarterly Report for the Implementation Plan for Board Recommendation 98-2, for the Period January 1 through March 31,2004 |
PDF |
|
6/24/2004 |
David E. Beck |
John T. Conway |
DOE Authorized Startup of the W78 Seamless Safety for the 21st Century Process as Required by Commitment 4.4.5 to Recommendation 98-2 |
PDF |
|
8/6/2004 |
M. Schoenbauer |
John T. Conway |
DOE Quarterly Report for the Implementation Plan for Board Recommendation 98-2, Accelerating Safety Management Improvements at the Pantex Plant, for the Period April 1 through June 30,2004. |
PDF |
|
11/3/2004 |
John T. Conway |
Spencer Abraham |
DOE Quarterly Report for the 98-2 Implementation Plan and the NNSA Exemption Extension Approvals for the W87 and W88 Weapons Program |
PDF |
|
12/14/2004 |
John T. Conway |
Spencer Abraham |
Board Issues a Reporting Requirement for Monthly Briefing from Senior NNSA Managers on the Status of Commitments under the Recommendation 98-2 Implementation Plan |
PDF |
|
12/14/2004 |
John T. Conway |
Spencer Abraham |
Board Issues a Reporting Requirement to DOE Establishing a Monthly Requirement for a Briefing on the Status of Commitments under the Recommendation 98-2 Implementation Plan |
PDF |
|
1/28/2005 |
M. Schoenbauer |
John T. Conway |
Quarterly Report for the 98-2 Implementation Plan, Safety Management at the Pantex Plant, for the Period October 1 - December 31, 2004 |
PDF |
|
8/4/2005 |
Xavier Ascanio |
A. J. Eggenberger |
Quarterly Report for the 98-2 Implementation Plan for the Period April 1 through June 30, 2005 |
PDF |
|
10/28/2005 |
Xavier Ascanio |
A. J. Eggenberger |
DOE Forwards the Quarterly Report for the 98-2 Implementation Plan for the Period July 1 through September 30, 2005 |
PDF |
|
12/14/2005 |
A. J. Eggenberger |
Samuel W. Bodman |
Board Issues a Reporting Requirement for a Report within 30 Days Providing a Path Forward for Required Guidance on Technical Business Practice |
PDF |
|
1/26/2006 |
Samuel W. Bodman |
A. J. Eggenberger |
DOE Path Forward for Guidance to Evaluate and Document Weapon Responses Relative to Commitment 4.2.2 in Revision 1 of the 98-2 Implementation Plan |
PDF |
|
8/16/2006 |
A. J. Eggenberger |
Linton Brooks |
Board Issues a Reporting Requirement for a Briefing within 30 Days on NNSA's Path Forward to Fulfill Commitment 4.2.2 of the Implementation Plan for Recommendation 98-2 |
PDF |
|
12/15/2006 |
A. J. Eggenberger |
Thomas P. D'Agostino |
Board Requests that NNSA Provide a Completion Date for the Final Assessment Report (DOE Commitment 4 .5.1) Recommendation 98-2 |
PDF |
|
3/13/2007 |
William S. Goodrum |
A. J. Eggenberger |
DOE Reports Completion of Commitments 4.2.2,4.4.6, and 4.5.1 in the 98-2 Implementation Plan, Safety Management at the Pantex Plant |
PDF |
|
5/10/2007 |
A. J. Eggenberger |
William C. Ostendorff |
Board Issues a Reporting Requirement for a Report within 30 Days Regarding Expectations and Actions in Accordance with the Revised DOE-STD-3016 |
PDF |
|
5/10/2007 |
A. J. Eggenberger |
William C. Ostendorff |
Board Issues a Reporting Requirement for a Report within 30 Days to Clarify NNSA's Expectations of the Revised DOE-STD-3016 |
PDF |
|
9/30/2008 |
Thomas P. D'Agostino |
A. J. Eggenberger |
DOE letter Reporting Completion of Recommendation 98-2, Revised Implementation Plan for Accelerating Safety Management Improvements at the Pantex Plant |
PDF |
|
3/5/2009 |
Thomas P. D' Agostino |
A. J. Eggenberger |
DOE Response to Board Letter of December 16, 2008, Documenting Concerns on Disposition of Findings Resulting from Nuclear Explosive Safety Studies and NES Change Evaluations |
PDF |