TRANSMITTED TO M. WHITAKER 8/14/95
DEFENSE NUCLEAR FACILITIES SAFETY BOARD
May 2, 1995
MEMORANDUM FOR: G.W. Cunningham, Technical Director
COPIES: Board Members
FROM: Larry Zull, Fernald Program Manager
SUBJECT:Trip Report - Review of UNH Project and CRU-4
VitrificationPilot Plant at Fernald
- Purpose: This trip report documents a February 23-24, 1995 visit
to the Fernald site to review the status of the Uranyl Nitrate Hexahydrate (UNH)
Neutralization Project,Unit-4 (CRU-4) Vitrification Pilot Plant, and other
on-going activities. Defense Nuclear Facilities Safety Board (Board) staff
members Randall Robinson, Andrew Stadnik, and Larry Zull participated in the
reviews.
- Summary:
- The UNH Neutralization project has been in violation of an Ohio
Environmental Protection Agency (OEPA) Order to begin neutralization/removal of
the UNH since January 17, 1995. The UNH project has not been able to begin the
neutralization because of equipment problems. An independent design review of
the UNH systemequipment identified several design, procurement, and installation
problems which are being addressed by corrective action plans. Contractor and
Department of Energy DOE) Operational Readiness Reviews (ORRs) must also be
performed before UNH neutralization operations can begin. The latest Fernald
Environmental Restoration Management Company (FERMCO) and DOE schedule shows UNH
processing beginning by July 20, 1995.
- b. The CRU-4 Vitrification Pilot Plant, currently under
construction, will demonstrate the retrieval and vitrification of residues from
previous uranium processing operations. Carbon filters are used in the off-gas
treatment system to reduce radon emissions; however, other technologies, such as
cryogenics, can reduce radon emissions to near zero. A planned follow-on
full-scale vitrification facility may release twenty times as much radon as the
pilot plant. FERMCO may want to consider cryogenic technology to reduce radon
emissions from a future full-scale plant.
-
Background:
- The purpose of the UNH Neutralization Project is to neutralize 200,000
gallons of acidi UNH contained in 18 tanks at the Fernald site, and ship the
resulting radioactive materials to the Nevada Test Site. The contractor, FERMCO,
designed a system to neutralize and process the UNH material for off-site
shipment to the Nevada Test Site. However, design and operational problems,
including a cracked piping weld, were\identified during system Operability
Testing in December 1994. Testing and operations were then suspended by FERMCO
while an independent design review of the UNH system was performed. The UNH
project is currently in violation of an OEPA Order to begin
neutralization/removal of the UNH by January 17, 1995.
- The CRU-4 Vitrification Pilot Plant program will demonstrate the retrieval
and vitrification of residues from uranium processing operations in the 1950's.
The residues, which contain high-activity concentrations of radionuclides
(including radium and thorium) and cold metal oxides, are contained in Silos 1,
2, and 3. The vitrification pilot plant is a one metric ton (2,200 lbs) per day
facility to process the residues. The CRU-4 Vitrification Pilot Plant program
will be conducted in two phases. Phase I will demonstrate operation with
non-radioactive surrogate materials, while Phase II will involve the
vitrification of actual silo residues. Concurrent FERMCO and DOE Readiness
Assessments for Phase I operations are scheduled to begin July 3, 1995.
- Discussion: The Board staff review consisted of DOE and FERMCO
presentations, technical discussions, a tour of the UNH Neutralization project
facilities, and a tour of the CRU-4 Vitrification Pilot Plant facilities.
- UNH Neutralization Project:
- The FERMCO independent design review of the UNH project concluded that:
(1) certain piping systems were unnecessarily constrained, which could
potentially result in stresses exceeding code allowables; (2) secondary
confinement piping, required by DOE Order 6430.1A, was only partially
incorporated in the design, and not formally waived prior to construction of the
piping system; (3) the single case of weld failure was attributed to poor weld
quality due to improper fit-up, tightly butted root faces, and extensive lack of
penetration; (4) the double diaphragm pumps were installed and tested without
adequate engineering justification, and the installation did not comply with the
mounting details; (5) schedule constraints drove the installation and testing of
the double diaphragm pumps prior to establishment of a revised
instrumentation/control design; and (6) purchase order records lacked complete
documentation, and field changes were not controlled. Corrective actions to
address these concerns included inspections of other piping welds, and
replacement of the double diaphragm pumps withprogressive cavity pumps.
- In late January 1995, the seventh contractor program manager and
management team were installed. The latest FERMCO and DOE schedule has been
released, which shows UNH processing beginning by July 20, 1995, and finishing
in April 1996. Contractor and DOE Operational Readiness Reviews must be
performed before UNH neutralization operations can begin.
- CRU-4 Vitrification Pilot Plant: The major design features of the
Vitrification Pilot Plant were discussed by FERMCO. The Board staff reviews
included discussion ofradon emissions from the plant.
- Radon Emission Limits: Radon-222 gas is generated as a result of
the radioactive decay of the radium-bearing residues to be vitrified. The CRU-4
Vitrification Pilot Plant is a treatment plant, not an interim storage or
disposal facility. Chapter IV in DOE Order 5400.5, Radiation Protection of the
Public and the Environment, provides radon emission limits for interim storage
and long-term management (disposal) facilities; however, there are no
requirements for emissions from a treatment plant. The only radon emission limit
applicable to the pilot plant is that the average annual radon concentration
should not exceed 3 pCi/L above background at any location outside the site
boundary. This limit includes radon emissions from all on-site sources,
including pilot plant operations. Compliance with the 3 pCi/L limit will be
determined by monitoring at various locations at the site boundary.
- Off-Gas Treatment System (OGTS): The purpose of the OGTS is to
treat off-gas from the melter/furnace to meet emission standards, and to reduce
radon emissions. Carbon filters are used in the OGTS to allow for decay (3.82
day half-life) of a portion of the radon-222 gas released during the
vitrification process. Discussions with FERMCO revealed that the performance of
the carbon filters with radon is not well known. The radon removal efficiency
of the carbon filters may only be 85%, rather than the assumed design efficiency
of 95%. An efficiency of only 85% will result in a radon concentration of 210
pCi/L from the stack during operations.
The purpose of the CRU-4 Vitrification Pilot Plant is to demonstrate
that the designis workable as a full-scale industrial plant. Using the same
carbon filter technology as the pilot plant, the follow-on full-scale
vitrification plant could release twenty times as much radon as the pilot-plant.
Other technologies, such as cryogenic systems, could reduce radon emissions to
near zero. FERMCO may want toconsider other technology to further reduce radon
emissions from the full-scale vitrification plant.
- Thorium Overpack Project: In this project, approximately 5,600
drums of thorium materials in Building 65 will be prepared for disposal by
placing them in overpack containers suitable for off-site shipment to the Nevada
Test Site. Planning for the overpack includes one independent design review and
FERMCO and DOE ORRs. The project is scheduled to begin overpacking operations
in November 1995, and finish in December 1996. The staff was provided a copy of
the latest schedule, and a 90 percent draft of the Safety Analysis Report. The
staff plans to conduct additional reviews as the project progresses.
- Technical Management Plan: EM-423 has conducted two reviews to
assess the DOEFernald Area Office (DOE-FN) implementation of the Technical
Management Plan (TMP). A TMP baseline assessment was performed in October 1994,
and a UNH Project interim compliance assessment was performed in December 1994.
The UNHassessment found that personnel appeared qualified, but required greater
familiarity with the safety basis documentation and the Unreviewed Safety
Question process. A better understanding of the TMP was also required. A
corrective action plan was developed to address the findings. EM-423 plans to
conduct another UNH assessment prior to the DOE ORR in June 1995. The Fernald
Environmental Management Project Division, EM-423, has also developed a draft
TMP for their activities. The EM-423 TMP compliments the Fernald Area Office
TMP.
- DOE FAR Manual: On December 2, 1994, DOE Secretary O'Leary issued
a letter to DOE program office and field managers requesting acknowledgement of
compliance with responsibilities in the "Manual of Functions, Assignments,
and Responsibilities for Nuclear Safety", also known as the DOE FAR Manual.
Many of the DOE-FN personnel interviewed by the staff were not aware of the FAR
Manual or its contents.
- Future Staff Actions: The staff intends to conduct additional
reviews of the CRU-4 Vitrification Pilot Plant project design.