March 14, 1997
| TO: |
|
G. W. Cunningham, Technical Director |
| FROM: |
|
P.F. Gubanc & D.G. Ogg, Hanford Site Representatives |
| SUBJECT: |
|
Activity Report for Week Ending March 14, 1997 |
Mr. Ogg was in training three days this week to complete Radworker II annual training, Hazardous Waste Operations training (8 hr), annual physical certification, and annual respirator training and mask fit.
A. Tank Sampling Resumption: As discussed in last week's report, DOE-RL placed a hold on tank push-mode core sampling due to questions regarding the adequacy of the authorization basis (AB). On March 8, 1997, DOE-RL amended their prior direction of March 1, as follows:
While some AB interpretation questions remain, they can be resolved on a non-controlling basis. We agree with DOE-RL's current direction and guidance.
B. K-Basins Radcon Improvements: In the past, the Board's site representatives noted radiological control practices at the K-Basins that were not consistent with good radiological conduct of operations. One practice involved post-job workers who had not been surveyed after doffing their anti-contamination clothing, and who could be potentially contaminated, sharing the same buffer area as pre-job workers. As the post-job workers made their way approximately thirty feet to the whole body counter, they crossed paths with, and could potentially contaminate, pre-job workers. A second poor practice involved a requirement imposed by facility management that all workers, upon exiting a contamination area, use a PCM-1B half-body monitor and receive a whole body frisk for beta/gamma and alpha contamination from a qualified radcon technician. This practice, while conservative, was not an effective use of resources and could foster a mistrust of either the PCM-1B or the whole body frisk performed by the radcon technician.
In recent weeks, K-Basins personnel completed actions that correct these two problems. Workers are just completing construction on vestibules in both KW and KE Basins that will allow post-job workers to exit the basin area through a different path than that used by pre-job workers to enter the basin area. Additionally, facility management has removed the requirement that all workers receive a whole body frisk from the radcon technicians as long as they successfully pass through the PCM- 1B. Workers still have the option of requesting a whole body frisk from the radcon technician if they so desire.
C. Tank Farm Labeling and Drawings: As reported on February 7, tank farms has established a labeling and drawing upgrade project. The project is tasked on a farm-by-farm basis to perform, or track completion of, the following actions:
Each of the above actions must be coordinated and sequenced with the others to assure a smooth transition and to minimize confusion. Within the next few weeks, the contractor expects to relabel BX farm, which was selected for its relative simplicity. Mr. Gubanc is closely reviewing the preparations and process to relabel BX farm to assure that each of the above actions is fully executed and that they are well integrated.
cc: Board Members