DEFENSE NUCLEAR FACILITIES SAFETY BOARD

April 25, 1997

TO:
 

G. W. Cunningham, Technical Director

FROM:
 

R.F. Warther, M.T. Sautman

SUBJECT:
 

RFETS Activity Report for Week Ending April 25, 1997

Recommendation 94-3. As reported in the Board Staff's trip report last week, K-H has assigned a single individual to manage Recommendation 94-3, including efforts to complete the BIO and implement B371 priority upgrades. He also is tasked with providing a detailed answer to the question of explaining why K-H believes B371 is safe for continued operations. Based on discus sions among Dr. Eggenberger, the Site Reps and Board Staff the K-H manager intends to prepare a matrix similar to that below. Data is example data only.

Document Requirement 1988 TSR 1997 draft BIO OSR Implement Status
Ventilation change in P 0.3" zone I/zone II change in P 0.5" zone I/atmos change in P 0.1" zone III/atmos Fully implemented
Conduct of Maintenance Not required Per Site Conduct of Maintenance Manual Partially implemented

This matrix will be completed over the next several weeks. In addition to this deliverable, K-H intends to provide RFFO with a detailed schedule for the BIO, BIO implementation plan, and priority upgrades this week.

Recommendation 94-1. The Site Reps inspected the packaging sections of the Plutonium Stabilization and Packaging Systems, which is being set up at an off-site facility. It looks extremely impressive. Delivery of the stabilization sections is running about 10 weeks behind schedule.

Performance Measures. RFFO continues its efforts to evolve performance measures. The RFFO Manager has been working with the AM for Policy and Planning to develop specific long term performance measures that clearly focus K-H's efforts. For example, RFFO is considering a set of measures that would require removal of all SNM from one of the buildings in the protected area, removal of the drums, and at least a partial deconstruction of the building. This measure would effectively subsume several other potential performance measures, including mortgage reduction within the PA, removal of drums from the Protected Area (a RFCA milestone) and operation of B440 (the likely repository for TRU and LLW drums). Draft FY98 performance measures will not be available for several months yet.

Electrical. Due to heavy precipitation Wednesday night, water leaked through a metal sheath and caused a short between two bus bars in B707. These bars connect the transformer to the switchgear located on the second floor. The short caused a power loss to the facility. All nuclear operations have been terminated. The emergency generator is providing power to the facility's vital loads until the bus line is repaired. The repairs and testing are expected to be completed Tuesday. In addition to the emergency generator, there is a 1400 kW generator on standby and the building has an uninterruptible power supply.

Vaults. General observations of the vault walkdowns are listed below. The attached table (which contains UCNI material) provides additional information.

From discussions with facility representatives, some of them had not been in any of the vaults in their facility. although the vaults are entered on a fairly frequent basis, some vaults had not been entered for years by any facility representative.

cc: Board Members