Recent Board Activity

Date Title Author Typesort icon Download
12/23/1997 Board re: 95-2 Implementation Plan, Issues a Reporting Requirement for a Report within 60 Days for the Status of Each of the Requisites for an Integrated Safety Management Program with Supporting Documents John T. Conway Letter application/pdf iconPDF
12/29/1997 DOE Completion of Commitment 5.2.2.a in Implementation Plan 92-4 Revision 2N, Multi-Function Waste Tank Facility at the Hanford Site John D. Wagoner Letter application/pdf iconPDF
12/29/1997 DOE Forwards the Los Alamos National Laboratory Site Assessment Report for the 97-1 Implementation Plan Bruce G. Twining Letter application/pdf iconPDF
12/23/1997 DOE Recommendation 96-1 Implementation Plan Program Status Roy J. Schepens Letter application/pdf iconPDF
12/22/1997 DOE Functions, Responsibilities, and Authorities Manuals (FRAMs) Federico Peña Letter application/pdf iconPDF
12/19/1997 DOE Committment 5.2.2.e for the 92-4 Implementation Plan John D. Wagoner Letter application/pdf iconPDF
12/17/1997 Senate Concerns Regarding Hanford Tank Farms John Glenn Letter application/pdf iconPDF
12/15/1997 DOE Response to Board June 5, 1997, Letter Regarding Recommendation 95-1 Ray A. Hunter Letter application/pdf iconPDF
12/12/1997 DOE Forwards the Recommendation 97-2 Implementation Plan Federico Peña Letter application/pdf iconPDF
12/9/1997 Current List of Orders of Interest to the Board Ronald W. Barton Letter application/pdf iconPDF
12/8/1997 Board Comments on the Rate of Progress on Complex-Wide Integration of Actions Responding to Recommendation 94-1 John T. Conway Letter application/pdf iconPDF
12/5/1997 Board Evaluation of DOE's Draft Order 430.1A John T. Conway Letter application/pdf iconPDF
12/5/1997 Board Recommendations 93-1 and 95-2 in Relation to the 452-Series Orders, Standards, and Guide John T. Conway Letter application/pdf iconPDF
11/21/1997 DOE Quarterly Progress Report for the 94-2 Implementation Plan Alvin L. Alm Letter application/pdf iconPDF
6/9/2011 Board Addresses Concerns about Boreholes Near Tank C-105 at the Hanford Site Peter S. Winokur Letter application/pdf iconPDF
11/25/1997 DOE Fourth Quarterly Report for the 94-3 Implementation Plan Alvin L. Alm Letter application/pdf iconPDF
11/18/1997 Board Forwarding Technical Report DNFSB/TECH-17, Review of the Hanford Spent Nuclear Fuel Project (Recommendation 94-1) John T. Conway Letter application/pdf iconPDF
9/24/1998 DOE Forwards Responses from Field Elements on Fire Safety Programs Peter N. Brush Letter application/pdf iconPDF
9/18/1998 DOE Forwards Comments on the Surveillance of Nuclear Weapon High-Explosive Operations at Pantex Report Gene Ives Letter application/pdf iconPDF
11/14/1997 DOE Completion of Milestones for the Revision of the 93-5 Implementation Plan John D. Wagoner Letter application/pdf iconPDF
9/17/1998 DOE Forwards the Current and Planned Low-Level Waste Disposal Capacity Report, Revision 1, per the 94-2 Implementation Plan James M. Owendoff Letter application/pdf iconPDF
11/14/1997 House of Representatives re: Activities at Department of Energy Sites John M. Spratt, Jr. Letter application/pdf iconPDF
9/17/1998 DOE Forwards the Low-Level Waste Disposal Facility Federal Review Group Manual per the 94-2 Implementation Plan James M. Owendoff Letter application/pdf iconPDF
11/12/1997 Board Accepts the Revised 92-4 Implementation Plan John T. Conway Letter application/pdf iconPDF
9/16/1998 Board Comments on the Feedback and Improvement Process Report John T. Conway Letter application/pdf iconPDF
11/12/1997 Board re: the Ongoing Process of Reviewing and Evaluating the Content of Standards John T. Conway Letter application/pdf iconPDF
9/11/1998 DOE Forwards its Response to a Board Letter Regarding PFP (Recommendation 94-1) James M. Owendoff Letter application/pdf iconPDF
11/10/1997 DOE Implementation of Recommendation 94-3 at Rocky Flats Building 371 Alvin A. Alm Letter application/pdf iconPDF
9/11/1998 List of Selected Near Term Schedule Milestones for the Removal and Safe Storage of Deteriorating Spent Nuclear Fuel from the K-Basins John T. Conway Letter application/pdf iconPDF
11/7/1994 DOE In-Tank Precipitation Facility and Tank Farm Authorization Basis and Safety Programs Alvin A. Alm Letter application/pdf iconPDF
9/10/1998 Board Congratulates Secretary Richardson for his Appointment to the DOE John T. Conway Letter application/pdf iconPDF
9/10/1998 Board Letter Regarding Lack of DOE PSO's Response to a Deputy Secretary Memorandum Regarding the "Fire Safety Programs." John T. Conway Letter application/pdf iconPDF
11/3/1997 DOE Tenth Quarterly Report for July 1 - September 31, 1997 for the 94-1 Implementation Plan Alvin A. Alm Letter application/pdf iconPDF
9/9/1998 Report on the Status of Recommendation 94-1 Milestones at the PFP and its Efforts in Place to Improve the Readiness Review Process Ernest J. Moniz Letter application/pdf iconPDF
9/2/1998 Board Announcement Scheduling a Public Hearing Regarding Recommendation 95-2 on September 22, 1998, 9:00 a.m. DNFSB Letter application/pdf iconPDF
10/31/1997 DOE Completion of Milestone 5.6.3.1.f, for the 93-5 Implementation Plan John D. Wagoner Letter application/pdf iconPDF
9/2/1998 Technical Update per the 94-1 Implementation Plan Bill Richardson Letter application/pdf iconPDF
10/31/1997 DOE Report on Catalytic Decomposition of Soluble Tetraphenylborate (TPB) Studies, to Update Milestone 5.2.2-1 for the 96-1 Implementation Plan Frank R. McCoy, III Letter application/pdf iconPDF
9/2/1998 Quarterly Progress Report per the 94-3 Implementation Plan James M. Owendoff Letter application/pdf iconPDF
10/30/1997 DOE re: Delays on the Integrated Safety Management Systems Guide (G-450.4-1) Recommendation 95-2 Richard C. Crowe Letter application/pdf iconPDF
10/30/1997 Board Grants Extension for Technical Report on Lightning Protection for High Explosives at Pantex John T. Conway Letter application/pdf iconPDF
6/8/2011 DOE Requests 30 Day Extension on Two Deliverables for Recommendation 2009-2, Los Alamos National Laboratory Plutonium Facility Seismic Safety, Implementation Plan James J. McConnell Letter application/pdf iconPDF
10/29/1997 DOE Quarterly Report for July 1 - September 30, 1997, for the 93-3 Implementation Plan Archer L. Durham Letter application/pdf iconPDF
10/29/1997 DOE Changes to Recommendation 94-1 for the Safe storage of Potentially Critical Materials at Two Facilities at the Oak Ridge Reservation Federico Peña Letter application/pdf iconPDF
10/28/1997 DOE Response to the Board's Trip Report on W69 HAR at Pantex Gene Ives Letter application/pdf iconPDF
10/24/1997 DOE Documentation Completing Commitment 5.5.2.(d) Revision for the 92-4 Implementation Plan John D. Wagoner Letter application/pdf iconPDF
10/28/1997 DOE Requests an Additional 45 Days to Complete the 97-2 Implementation Plan Federico Peña Letter application/pdf iconPDF
10/22/1997 Board Reviews DOE Report on Material Handling at Hanford Plutonium Finishing Plant John T. Conway Letter application/pdf iconPDF
10/21/1997 Board Accepts Recommendation 97-1 Implementation Plan John T. Conway Letter application/pdf iconPDF
10/21/1997 DOE Response to the Board's Report of September 12, 1997, Concerning Lightning Protection for Collocated High Explosives and Nuclear Materials at the Pantex Plant Gene Ives Letter application/pdf iconPDF