August 17, 2001 |
DOE Letter Regarding a new Anticipated Delivery Date to Develop a Replacement Schedule for the Pantex Plant Fire Alarm System |
Letter |
PDF |
September 25, 2001 |
Board Concerns about the Justification for Continued Operations for W88 Activities and Accepts Interim Safety Controls |
Letter |
PDF |
October 2, 2001 |
Board Issues a Reporting Requirement for DOE to Provide a Briefing within 30 Days Containing Details on Procedural Compliance Issues at Pantex and the Corrective Actions Proposed by DOE |
Letter |
PDF |
December 7, 2001 |
DOE Letter Enclosing Two Deliverables for Implementation Plan 98-2, Revision 1 |
Letter |
PDF |
January 3, 2002 |
DOE Responding to Board Letter Regarding Justification for Continued Operations in relation to W88 Hazard Analysis Report |
Letter |
PDF |
February 4, 2002 |
DOE re: Pantex Plant Fire Alarm System Program Plan |
Letter |
PDF |
February 11, 2002 |
DOE Revised Section 11.8 of the Development & Production Manual Relating to the W88 Analysis Report |
Letter |
PDF |
February 28, 2002 |
DOE Pantex Plant Sealed Insert First Quarter Fiscal Year 2002 Summary Status Report, a Deliverable under Commitment 5.2.2 of the Recommendation 99-1 Implementation Plan |
Letter |
PDF |
March 11, 2002 |
DOE Quarterly Report for Implementation Plan 98-2, Revision 1, for the Period Ending December 31, 2002 |
Letter |
PDF |
March 18, 2002 |
DOE Intent to Change Commitment 5.2.1 in Implementation Plan for Recommendation 99-1 |
Letter |
PDF |