September 6, 2012 DOE Response to Board June 18, 2012, Letter Requesting an Additional 60 Days beyond the 45 Day Initial Extension for further Development of Responses to the Board Reporting Requirement Concerning the Plutonium Facility, Los Alamos National Laboratory Letter PDF iconPDF
August 14, 2012 DOE Reply to Board July 18, 2012, Letter Regarding the Los Alamos National Laboratory Plutonium Facility (PF-4), Stating that the National Nuclear Security Administration will Require until September 28, 2012, to Provide the Board with a Detailed Response Letter PDF iconPDF
July 31, 2012 DOE Requires an Additional 60 Days beyond the Requested 60-Day Time Frame to Complete the DOE Response to Board June 11, 2012, Letter Regarding the Transuranic Waste Treatment Facility (TWF) Project at the Los Alamos National Laboratory (LANL) Letter PDF iconPDF
July 18, 2012 Board Issues a Reporting Requirement Concerning Seismic/Structural Analysis at the Plutonium Facility, Los Alamos National Laboratory Letter PDF iconPDF
July 13, 2012 DOE Response to Board June 18, 2012, Letter Concerning the Plutonium Facility at the Los Alamos National Laboratory (LANL) Letter PDF iconPDF
June 11, 2012 Board Issues a Reporting Requirement for a Report Identifying Actions Taken or Planned by the NNSA to Resolve Safety Issues Relating to the Transuranic Waste Facility (TWF) Project at Los Alamos National Laboratory (LANL) Letter PDF iconPDF
March 20, 2012 DOE Letter Informing the Board that DOE has Completed Deliverable 5.4.4 of the Implementation Plan (IP) for Recommendation 2009-2, Los Alamos National Laboratory, Plutonium Facility Seismic Safety Letter PDF iconPDF
January 30, 2012 DOE Explanation of its Conclusion that Operations at Los Alamos National Laboratory's Plutonium Facility (PF-4) Adequately Protect Public Safety Letter PDF iconPDF
November 18, 2011 DOE Fulfills February 28, 2011, Commitment to Board that the National Nuclear Security Administration (NNSA) Would Inform the Board Concerning Proposals for Reducing Costs of the Chemistry and Metallurgy Research Building Replacement (CMRR) Project Letter PDF iconPDF
November 15, 2011 DOE Letter Informing the Board that DOE has Completed Deliverable 5.2.3 of the Implementation Plan (IP) for Board Recommendation 2009-2 Letter PDF iconPDF